Further Maths Transportation problems Practice Questions
Free Further Maths Transportation problems practice questions with full step-by-step worked solutions. Covers transportation, tableau, degeneracy, balancing. Practise exam-style problems and check your method.
The table below shows the cost (in pounds) of transporting one unit from each supply point Si to each demand point Dj, together with the supplies and demands. S1S2S3DemandD147714D23551D39987Supply1075 Find the total supply available.
Show worked solution
Worked solution
Read the supplies from the table
s1=10,s2=7,s3=5
The supply of each source is the entry in the final column of its row.
Add the supplies together
10+7+5=22
The total supply is the sum of the individual supplies.
State the total supply
total supply=22
This is how many units are available in total.
Answer
22
Question 2
2 markseasy
The table below shows the cost (in pounds) of transporting one unit from each supply point Si to each demand point Dj, together with the supplies and demands. S1S2S3S4DemandD1822611D258667D379725D474873Supply12455 Using the north-west corner method, state the number of units allocated to the cell in row S1, column D1.
Show worked solution
Worked solution
Apply the north-west corner rule
allocate min(si,dj) starting at the top-left cell
Each step fills the current top-left cell and crosses out an exhausted supply or demand.
These are the occupied cells of the north-west corner basic feasible solution.
State the allocation
x11=11
This is the north-west corner allocation for that cell.
Answer
x11=11
Question 3
4 marksintermediate
The table below shows the cost (in pounds) of transporting one unit from each supply point Si to each demand point Dj, together with the supplies and demands. S1S2S3DemandD147512D28365D32423Supply6410 The problem is formulated as a linear programme with xij the number of units sent from Si to Dj. Which of the following is the supply constraint for S3?
Show worked solution
Worked solution
Recall that supply and demand must be met exactly
j∑xij=si,i∑xij=dj
In a balanced problem every supply is used up and every demand is filled.
Write the required constraint
x31+x32+x33=10
The relevant variables sum to the supply.
Recall what a transportation problem asks
mini∑j∑cijxij
The aim is to meet every demand from the available supplies at least total cost.
Recall the balance condition
i∑si=j∑dj
A transportation problem can only be solved once total supply equals total demand.
Recall how a dummy restores balance
dummy supply or demand=i∑si−j∑dj
A dummy row or column with zero costs absorbs the surplus, leaving a balanced problem.
Recall the number of occupied cells needed
occupied cells=m+n−1
A non-degenerate basic feasible solution of an m×n problem fills exactly m+n−1 cells.
State the constraint
x31+x32+x33=10
This is one of the equality constraints of the transportation LP.
Answer
x31+x32+x33=10
Question 4
6 markshard
The table below shows the cost (in pounds) of transporting one unit from each supply point Si to each demand point Dj, together with the supplies and demands. S1S2S3DemandD13267D23754D39863D43726Supply974 Find the north-west corner solution and, taking u1=0, determine the shadow cost u2.
Show worked solution
Worked solution
Apply the north-west corner rule
allocate min(si,dj) starting at the top-left cell
Each step fills the current top-left cell and crosses out an exhausted supply or demand.
Each occupied cell gives one equation ui+vj=cij.
Solve the equations taking u1=0
u1=0,u2=4,u3=−1,v1=3,v2=3,v3=4,v4=3
With u1=0 the remaining potentials follow one occupied cell at a time.
Read the required potential
required potential u2=4
The potential is read from the solved shadow-cost equations.
Recall what a transportation problem asks
mini∑j∑cijxij
The aim is to meet every demand from the available supplies at least total cost.
Recall the balance condition
i∑si=j∑dj
A transportation problem can only be solved once total supply equals total demand.
Recall how a dummy restores balance
dummy supply or demand=i∑si−j∑dj
A dummy row or column with zero costs absorbs the surplus, leaving a balanced problem.
Recall the number of occupied cells needed
occupied cells=m+n−1
A non-degenerate basic feasible solution of an m×n problem fills exactly m+n−1 cells.
State the shadow cost
u2=4
This potential satisfies ui+vj=cij on the occupied cells.
Answer
u2=4
Question 5
9 markschallenging
The table below shows the cost (in pounds) of transporting one unit from each supply point Si to each demand point Dj, together with the supplies and demands. S1S2S3DemandD13834D24337D385711Supply7105 Starting from the north-west corner solution, perform one stepping-stone iteration and find the resulting total cost.
Show worked solution
Worked solution
Apply the north-west corner rule
allocate min(si,dj) starting at the top-left cell
Each step fills the current top-left cell and crosses out an exhausted supply or demand.
The entering cell gains θ units and the minus cells lose them.
Cost the new allocation
new cost=101+(4)(−2)=93
The cost changes by θ times the entering improvement index.
Recall what a transportation problem asks
mini∑j∑cijxij
The aim is to meet every demand from the available supplies at least total cost.
Recall the balance condition
i∑si=j∑dj
A transportation problem can only be solved once total supply equals total demand.
Recall how a dummy restores balance
dummy supply or demand=i∑si−j∑dj
A dummy row or column with zero costs absorbs the surplus, leaving a balanced problem.
Recall the number of occupied cells needed
occupied cells=m+n−1
A non-degenerate basic feasible solution of an m×n problem fills exactly m+n−1 cells.
Recall the north-west corner rule
start at the top-left cell and allocate as much as possible
Each allocation exhausts a supply or a demand, and we move right or down accordingly.
Recall the shadow-cost equations
ui+vj=cij on every occupied cell
Fixing u1=0 makes the potentials ui and vj uniquely determined.
Recall the improvement index
Iij=cij−ui−vj
The improvement index measures the change in cost from sending one unit through an empty cell.
State the new total cost
new cost=93
This is the cost after one stepping-stone iteration.
Answer
93
Unlock 65 more Transportation problems questions
Create a free account to work through every Further Maths Transportation problems question with instant step-by-step worked solutions, progress tracking and interactive lessons.